October 10, 2018
By Richard Crumbacker
Crisfield-Somerset County Times
PRINCESS ANNE — If a proposal by
Chesapeake Utilities to deliver natural gas to ECI and UMES is accepted by
Maryland Environmental Service (MES), a new lower- cost energy source
could be available to homes and businesses in upper Somerset County
within three years. Chesapeake Utilities would be required to have gas line
installed by Dec. 2021
The Dover-based company answered a request for
proposals (RFP) by MES to bring natural gas to the prison so it could
discontinue its chip-burning power plant, and to the university to
eliminate its reliance on fuel oil. It expects to hear for Chesapeake. “We’ve
been trying to get into Somerset for some time,” he said. “We’re very keen not
to build a pipeline only for those two users” as “90 percent of our customer
base is residential.”
The model Chesapeake would like to follow here
is one that occurred in Delaware in 2012. A line 13.5 miles long ran from
Milton to Lewes and connected Beebe Healthcare, Allen Harim Foods, SBI Pharma
and Perdue. Along the way 2,200 residential and small commercial users hooked
up.
Once in place natural gas attracts new businesses
and can lead to business expansion, Mr. Holden said. In Cecil County an
extension of 5.7 miles to serve a mushroom grower resulted in a second mushroom
grower to open as well as a medicinal marijuana grower. In Princess Anne he
would be interested in serving the town’s industrial park if it’s needed.
As for residential customers, compared to
propane the savings can be $500 per year, he said, and “ bigger energy users
save more money.”
To serve the county, however, Chesapeake must show it has
customers that will essentially carry the load of the expansion so other
ratepayers are not burdened by the system’s growth. Transmission lines that end
at Commerce Street in Salisbury would be continued to Eden, and local
distribution pipe would run south to Revell’s Neck Road to ECI.
“We could do the project with ECI only,” Mr.
Holden said, and previous to the RFP the Department of Public Safety and
Correctional Services already said by letter if natural gas was available
it would seriously consider hooking up.
But without ECI, “ we could not make it an
economical project.”
Although Chesapeake is the only natural gas
provider on the shore, it must follow the state’s procurement process. Mr.
Holden said, “It will save them notable money.”
Somerset County is being asked to approve an
exclusive franchise agreement and Mr. Holden along with Director of Energy
Services Shane Breakie met with the County Commissioners in August and
provided them a draft contract which is still pending.
“They’ve asked us to hold until we get the
RFP…then come back and talk about it,” Mr. Holden said. He would then
request a similar arrangement with the Town Commissioners.
“To serve all of Princess Anne is an easy
endeavor,” he said.
If regulatory hurdles and permitting go smoothly
Mr. Holden said the timeline would be “quite a bit” shorter” than 2021, by
maybe as much as a year. “We could have gas flowing in 2020….that’s a very
viable target.”
The county and town would gain franchise fees
and taxes on the new infrastructure. Chesapeake last year paid some $2.7
million in taxes company- wide, so “there is some revenue there.”
“I don’t want to stir the public up only not
to have success,” Mr. Hold en said, “ but I’m optimistic.”
Interest in natural gas in recent times goes
back to 2007, and four years later Mr. Breakie met with the County
Commissioners about a draft franchise agreement but it was never finalized.
A company called Somerset Utilities received
from the county a non- exclusive franchise in 2013 but it did not move forward
and dissolved following a federal district court order in February 2016. It’s
plan was to bring gas from Wicomico County south to the Pocomoke River so it
would be available to Sysco.
If an arrangement with the town is approved
questionnaires to residents would be distributed to gauge household interest in
the service.